Gross Reservoir Expansion Project
Contractor INterest form
The Gross Reservoir Expansion Project is in the process of growing our contractor team. If your company is interested in joining the team, please complete the form below. The information gathered here will be provided to the qualified CMGC contractors in 2021.
Latest News / Blog
Gross Reservoir Seasonal Shuttle Operator Job
May 13, 2022 - Denver Water is hiring for seasonal recreation shuttle operators at Gross Reservoir. Additional information on the posting can be found here.
Gross Reservoir community information sessions
Denver Water invites Gross Reservoir neighbors to join us for information sessions on May 21, between 10 a.m. and 5 p.m., at the Coal Creek Canyon Improvement Association Hall. Gross Reservoir Expansion Project representatives will provide an update on project...
Gross Reservoir fully closed to recreation for 2-3 weeks in May to allow for construction of access improvements
COAL CREEK CANYON — May 2, 2022 — Denver Water will close all recreation access to Gross Reservoir beginning in early May as contractors build access improvements on the north side ahead of the upcoming boating season. The closure is expected to last two to three...
Survey activity on Gross Dam Road
Over the next two weeks, Denver Water’s contractors, Metcalf Archeological Consultants, will be conducting cultural resource surveys along Gross Dam Road. Surveys are scheduled to start the week of April 25. Residents can expect to see crews walking along the...
Dam foundation preparation, quarrying and site preparation activities at Gross Reservoir
Dam foundation preparation, quarrying and site preparation activities involving drilling and blasting are scheduled to begin at Gross Reservoir today, April 12. Please note: Blasting will only take place during daylight hours. Drilling and blasting activities are...
Heavy equipment to travel to Gross Reservoir Expansion Project site
March 28, 2022 - Between March 28 and April 2, weather permitting, Kiewit Barnard Joint Venture will mobilize large equipment to the Gross Reservoir Expansion Project site. This activity will consist of a maximum of four caravans over the course of two nights. Each...
First steps on Gross Reservoir expansion
Feb. 27, 2022 - TAP - After 20 years of preparation, first signs of construction work emerging in vicinity of dam. After nearly two decades of planning and permitting, Denver Water’s work to expand Gross Reservoir northwest of Denver is set to kick off. Over the...