Gross Reservoir Expansion Project

It takes a long time to build a dam 471 feet high. A lot of other preparatory work is required such as quarrying and preparing the existing dam and foundation for the new dam. This additional work and expected work shutdowns during the winter months could take as much as three additional years, with a total construction schedule totaling over four years. The project schedule for the dam construction scope is dependent on regulatory authorizations, but could start as early as 2019.

The first planned work supporting the project consists of road improvements to the roads accessing Gross Dam. Principally, Denver Water is evaluating improvements and/or traffic control options for the intersection at SH72 and Gross Dam Road, and to Gross Dam Road itself. These projects could occur as early as 2019.

It will take three years to mine the on-site quarry, one year prior to the start of construction and two years during construction. Quarry activities will include drilling, blasting, excavation and processing. Quarry work will typically be done during daylight hours. Truck traffic has been drastically reduced with the decision to quarry sand and gravel on-site.

Quarrying materials on-site has reduced that number to around 35 hauling trucks per day carrying cement and fly ash and around 100 construction and personal vehicles per day. Denver Water intends to design the quarry in a way that will reduce long-term viewshed impacts.

Denver Water recognizes the existing intersection at Highway 72 and Gross Dam Road  is unsafe for the expected traffic during construction. These improvements are permanent and will remain in place long after construction is complete. The volume of construction traffic would vary day-to-day and month-to-month depending on the time of year and the type of construction activities. Denver Water is committed to listening to community concerns about potential impacts and have investigated and made a number of changes to the project design including:

  • Reducing truck traffic on Hwy 72 and Gross Dam Road by 75 percent by quarrying sand and gravel at the reservoir site.
  • Developing traffic plans to improve the safety of the intersection at Gross Dam Road and Hwy 72 for the expected truck traffic.
  • Evaluating opportunities for alternative hauling schedules during dam construction.

Denver Water conducted studies on activities that will affect local residents in and around Coal Creek Canyon during construction. While some work, such as actual concrete dam construction, will require 24-hour construction. Denver Water will continue to seek community input from the affected communities throughout construction on such topics as traffic control plans, hauling traffic schedules, viewshed reclamation, tree removal and more. Denver Water is committed to working closely with residents to ensure safety and open communication throughout construction.

Gross Reservoir Expansion Project Update Reports

Denver Water is committed to keeping the community informed about the status of the Gross Reservoir Expansion Project. On a bimonthly schedule, Denver Water will publish a project update report that will provide interested stakeholder with valuable information regarding various component of the project. We hope the community, stakeholders, and recreationist find the information helpful and informative. If you have additional questions about these report, please email us.

Latest News / Blog

Request for Proposals for Pre- and Post-Construction Monitoring

Denver Water is soliciting proposals from qualified firms for a fluvial geomorphologist/fisheries biologist/ecologist or other related professional to perform baseline pre-construction and post-construction monitoring and reporting of the Williams Fork River...

Volunteers Needed for Trout Unlimited’s Ranch Creek Project

In 2017, the Colorado River Headwaters Chapter of Trout Unlimited, a Learning By Doing (LBD) partner, led the re-vegetation component of the Fraser Flats project by donating volunteer time and resources to prepare the planting design and coordinate three volunteer...